Civil & Structural

Segmental and precast construction

How a metro viaduct, a flyover or a warehouse frame gets built out of factory-made pieces — match-casting, launching girders, balanced cantilever, shear keys and grouted joints — and why the joints and the temporary condition are where the risk lives.

IntermediateInfrastructure & Buildings

Standards referencedfib Bulletin 74EN 1992-2IRC 112IS 456AASHTO LRFD

A cast-in-place bridge is built where it stands: falsework up, reinforcement fixed, concrete poured, cured, struck. On a greenfield site that is fine. Above a live arterial road in a city, it is close to impossible.

Precast segmental construction moves the work off site. Segments are made in a casting yard under factory conditions, trucked in at night and erected in days. It is why almost every elevated metro built since the 1990s looks the way it does, and the same logic — make the pieces somewhere controlled, connect them quickly on site — gives us precast warehouse frames, hollowcore floors and precast bridge beams.

The engineering shifts accordingly. The pieces are rarely the problem. The joints between them, and the half-built condition, are.

An elevated metro viaduct under construction, a launching girder spanning between two piers with a precast concrete box segment suspended from it and being lifted into position at the end of a completed span, crawler cranes and a hazy city skyline beyond.
Span-by-span erection with a launching girder. The segment in the air was cast months ago against the one already in place — which is why the casting sequence and the erection sequence are the same sequence.

Why it wins in a city

Cast in place Precast segmental
Where the work happens Over the road, for months In a yard, in parallel
Road occupation Continuous A few night possessions
Quality control Site conditions Factory conditions, repeated moulds
Weather sensitivity High Low for casting, moderate for erection
Programme Sequential span by span Casting and erection run in parallel
Up-front cost Lower Yard, moulds, launching girder
Suits One-offs, complex geometry Repetition

The economics turn on repetition. A casting yard and a launching girder are a large fixed cost that only makes sense across many identical spans — which is exactly what a metro corridor is.

Match-casting: the idea that makes it work

The joints between segments have no reinforcement crossing them. That is only acceptable if the faces bear on each other perfectly, and the way to guarantee that is to cast each segment against its neighbour.

Segment 6 is cast. Segment 6 is then moved to become one end of the mould for segment 7. The two faces are exact negatives. Repeat along the span.

Shear keys — a castellated profile cast into the faces — do two jobs. During erection they drop the segment into position. In service they carry vertical shear across a joint that has no bars through it. Box girders typically use large single keys on the webs and many small keys across the top and bottom slabs.

Epoxy is applied to the faces before closure. It seals the joint against water — the lesson of Ynys-y-Gwas — and while wet it lets the faces slide into full bearing under a temporary stressing force. It is not the structural connection.

The three erection methods

Three segmental erection methods drawn in elevation. Span by span shows a launching girder spanning between two piers carrying a full span of segments which are then stressed together before the girder launches forward. Balanced cantilever shows segments added in pairs either side of a pier head with the out of balance moment marked, the two arms growing outwards until a closure pour joins them mid span. Incremental launching shows a deck cast in a fixed yard behind an abutment and pushed out over the piers with a steel launching nose ahead of it and temporary sliding bearings on each pier.
Three ways to build the same viaduct. What decides between them is the site — what is underneath, how deep the valley is, and how many identical spans there are to amortise the plant.

Span by span. A launching girder sits on two piers, picks up a complete span of segments, holds them in line while the tendons are stressed, then self-launches to the next pier. Fastest for many equal spans of 25–50 m. This is the metro viaduct method.

Balanced cantilever. Segments are added in pairs, one each side of a pier head, so the arms grow outwards together and their moments on the pier largely cancel. Used for 60–250 m spans and wherever there is no ground to stand on — a river, a gorge, a live railway. The arms meet at a closure pour at midspan.

Incremental launching. The deck is cast in a fixed yard behind an abutment and pushed out over the piers, with a light steel launching nose ahead of it to reach the next pier before the deck cantilevers too far. Every section of deck passes over every pier, so it experiences sagging and hogging in turn and must be prestressed for both.

Precast in buildings and warehouses

The same logic, less glamorous and far more common:

  • Hollowcore slabs — pre-tensioned, voided, spanning 6–16 m without propping. The floor of most precast car parks and mezzanines.
  • Double-tee units — long-span roof and floor units for warehouses and car parks.
  • Precast columns and beams — bolted or grouted connections, whole frames erected in days.
  • Precast wall panels and cladding — often the fastest way to close a building in.

What an inspector looks at

Where What Why it matters
Segment joints Opening, stepping, staining, efflorescence Prestress loss or water entering the ducts
Shear keys Cracking or spalling at the keys Shear transfer failing across the joint
Anchorage pockets Rust staining, unsealed pockets Water into the tendon anchorage
Deck soffit Longitudinal cracking on a duct line Duct corrosion, or grout voids
Closure pours Cracking, cold joints The weakest concrete on a cantilever bridge
Bearings and joints Movement, debris, leakage See bearings and expansion joints
Precast bearings Spalled corners, displaced pads A lost bearing on a hollowcore unit is a collapse risk
Tie reinforcement Grouted, continuous, as detailed Robustness against progressive collapse

What to take away

  • Precast segmental wins on disruption and repetition, not on strength.
  • Match-casting makes a perfect joint possible, and ties erection order to casting order for good.
  • Shear keys carry shear, epoxy seals and lubricates, prestress is what holds it together.
  • Span by span for many equal spans, balanced cantilever for long ones and difficult ground, incremental launching where a casting yard can sit behind an abutment.
  • The half-built structure usually governs, and the tendon layout reflects that.
  • In precast buildings, the units are reliable and the connections are the risk — bearing length, pads, grout and ties.

Check your understanding

10 questions. Nothing is recorded — this is just for you.

1Why is precast segmental construction the default for urban metro viaducts?
2What is match-casting?
3What do shear keys on a segment face do?
4In a segmental deck the joints have no reinforcement crossing them. What holds the structure together?
5What is a launching girder used for?
6In balanced cantilever construction, why are segments added in pairs?
7Why is the temporary condition often more critical than the finished structure in segmental work?
8What is the purpose of the epoxy in a match-cast joint?
9A precast warehouse frame uses hollowcore units on precast beams. What is the usual weak point?
10Segments are erected out of their casting sequence on a match-cast span. What happens?

#civil#precast#segmental#metro#viaduct#bridges#warehouses#erection